PROGRESS REPORT
June 1st, 2025
- Installation of the Grease interceptor: plumber to make all connections, finalize connections, inspections by Denver authorities and backfill, concrete replacement.
- Fire Alarm Installation– reprogram system to separate TI space from base building during construction; demo existing duct detectors at AHUs which are to be replaced; begin running conduit and rough ins
- Continued mechanical, electrical and plumbing work. Ongoing coordination with Penterra base building regarding new core locations and parking spots that will need to be vacated for cores
- Procurement of kitchen and hospitality equipment
- Finalization of the furniture and fixtures and procurement