PROGRESS REPORT
May 1st, 2025
On-going and upcoming work for Penterra Plaza Restaurant.
- Grease Interceptor – installation of new trap along with plumbing lines and connections associated (Fred and I will schedule a coordination meeting with Mark, Shawn, and Paul regarding schedule, logistics, etc. prior to starting work)
- Plumbing – finalize additional core locations required, continue interior plumbing runs and infill of unused cores.
- Electrical – continue wall and ceiling rough-ins
- Mechanical – continue running ductwork
- Fire Alarm – begin rough-in layout
- Fire Sprinkler – begin rough-in layout, coordinate with Paul/base building
- Continue Inspections